How to Perform a Concrete Takeoff

With annual production in the area of 4.1 billion metric tons, cement is a big deal--used in everything from foundations, structures, pre-cast and cast-in-place panels to stucco, paving, and so many other aspects of construction. Indeed, so essential is concrete to the construction industry that it provides the basis for over 53,000 contracting companies. Concrete’s high compressive strength makes it ideal for bearing heavy loads and transferring weight throughout the structure. From simple slabs poured in place to extensive multi-story structures that seem to touch the sky, knowing how to calculate an accurate concrete takeoff is essential to your company's ability to complete a profitable project.

But why is developing a detailed and accurate concrete estimate so difficult? For starters, if you over-estimate the quantities of concrete you need, your bid may have an inflated price, which means you’ll lose your bid. Alternatively, underestimating how much concrete is needed may result in the lowest bid that enables your firm to win the project, while you lose profitability. If you order concrete based on inaccurate takeoff numbers, your order is likely to be inaccurate, increasing the likelihood of wasted material or delays while waiting for additional material to be delivered.

Therefore, to ensure your takeoff is the most accurate, you need to understand how to complete the entire takeoff process end-to-end quickly and efficiently. With this in mind, we’ve developed our new guide on how to develop a concrete takeoff.

How to Estimate a Concrete Takeoff

Regularly securing projects for your business involves estimating projects that often include a concrete estimate as part of the bid. This means that you'll need to review the plans carefully so that you can calculate the labor and materials needed to complete the project. If you’re unfamiliar with how to prepare a quantity takeoff, check out our post to brush up on the basics of estimating for construction projects.

Because the takeoff is essential to your estimating process, it’s critical that the several steps required to complete a concrete takeoff be handled carefully and methodically. Below we provide the 4 essential steps to completing an accurate concrete takeoff.

4 Essential Steps

Concrete takeoffs are typically based on several specific areas: labor, materials, overhead, and profitability. Labor covers the amount of time it will take to place and finish the concrete, from setting up forms to finishing up the last of the work. Materials can cover items that will be measured in terms of length, area, and volume, with concrete typically being the main component measured by volume, typically by cubic yards.

Overhead costs can include a wide range of expenses that you need to keep the doors open at your business, but are not directly related to the project. Overhead can include insurance, office staff, vehicles, software, rent, and similar costs that you'll need to pay whether you have active projects to work or not. Once you've calculated these aspects, you need to add profit margin onto the figures, which is vital to keep your company operating and profitable.

Working Through the Takeoff Process

In general, there are approximately 21 areas of concrete work that need to be estimated before starting a concrete project. However, not all projects require all 21 areas and most require only a few. But it’s a good idea to develop your concrete takeoff methodically by going through the list in the order below:

Concrete Takeoff Workflow
1) COLUMN FOOTINGS: hand excavated area, forms, concrete12) SLABS ON CORRUGATED FORMWORK: corrugated formwork, edge forms, finish area, concrete
2) WALL FOOTINGS: hand excavated area, forms, 2 by 4 keys, concrete.13) STAIRS ON FILL: sand fill, form risers, finish tread and riser, concrete
3) FOUNDATION WALLS: forms (in 4-foot heights), 2 by 4 keys, slab seat bearing, and concrete14) SHORED STAIRS: form risers, stair bottom, finish tread and riser, concrete
4) PIERS BELOW GRADE: forms, concrete15) STAIR LANDINGS: forms, finish, concrete
5) BUILDING SLABS ON FILL: sand fill, edge forms, expansion joints, finish area, and concrete16) PAN FILL STAIRS: finish, concrete
6) EXTERIOR COLUMNS: forms, concrete17) MISC CONCRETE IN BUILDING: forms, finish, concrete
7) INTERIOR COLUMNS: forms, concrete18) EXTERIOR SIDEWALKS: sand fill, edge forms, expansion joints, finish, concrete
8) EXTERIOR BEAMS: forms, concrete19) EXTERIOR PAVING: sand fill, edge forms, expansion joints, finish, concrete
9) INTERIOR BEAMS: forms, concrete20) EXTERIOR STRAIT CURBS: hand excavated area, forms, finish, concrete
10) SHORTENED FLAT SLABS: slab forms, edge forms, finish area, concrete21) EXTERIOR CURB & GUTTER: hand excavated area, forms, finish, concrete
11) METAL PAN SLABS: slab forms, edge forms, finish area, concrete

Again this is an exhaustive list and because every project’s different, you’ll need to skip any area in this list not pertinent to your project. In other words, if your project doesn’t include exterior curbs, simply skip section 21.

Step 1: Estimating Materials

To calculate the cost of materials, you'll need to use a careful, methodical approach to determine measurements, quantities, and similar information. To start, you'll work on your materials takeoff using the list above. Reviewing the plans, you can start from the bottom of one corner, work across that level, and then move up to the next level, taking care to note every piece of rebar, square-foot of reinforcing mesh, or similar materials.

Once you’ve taken note of every material needed for the project, it’s now time to start estimating how much concrete will be needed and what type.

Although every job is different, whether estimating column footings, wall footings, foundation walls, or slabs, you’ll use the same basic formula. You’ll measure off the area and calculate the volume of concrete needed: length x width x depth. You’ll also want to add in an additional cost for waste and spillage, which is roughly 10% of the total volume.

Formula for calculating volume Length x Width x Depth (LxWxD)

To determine the amount of bags of concrete you’ll need, simply multiply the bags by the total cost. You can purchase concrete at a store for small projects, but for larger projects, you’ll definitely want to work with a ready-mix supplier.

And finally, you can finish estimating materials by calculating any additional materials needed beyond concrete, such as anchors. If you’re pouring concrete more than five inches deep, you’ll also need to add rebar (reinforcing bar) to help reinforce the entire structure of a commercial-level project or wire mesh for smaller residential projects. Although it's tempting to assume you’ll be calculating the cost of stainless steel rebar, there are five basic types of rebar to choose from with considerable price differences, including welded wire fabric, expandable metal, sheet metal, and epoxy coated rebar.

Beyond basic materials, you’ll need to think through other equipment you’ll need for the job and their costs. Here is a list of standard equipment you’ll need for most concrete projects:

Concrete Construction Equipment
MixersCompactorsWheelbarrows
FloatsScreedsVapour Retarders
ShovelsGroove CuttersSaws
Digging BarsRubber Boots & GlovesLevels
EdgersPolishersBrooms

Once you have a general idea of the cost of materials and made notations on the plans, you need to finalize the complete count of materials and their and their costs. Some companies still use paper and pencils, marking off areas on the plan as they complete their counts, though items can be marked off inaccurately. Others use PDF formats of plans and a spreadsheet, but it's fairly easy to accidentally change a formula on the spreadsheet, making errors problematic. Professional estimating software is an option, but it can be costly and has a long learning curve. Another great option is to use a cost estimating or takeoff service.

Step 2: Estimating Labor

Now that you’ve determined how much material is needed and its cost, you'll need to think about how long it will take to complete the project in terms of hours of labor and factor in the cost of that labor to your concrete takeoff. While calculating the labor involved, make sure to take into account shift differentials, union or non-union wages, overtime, time spent traveling up or down multi-story structures and similar aspects of the project that can impact labor costs.

It’s also wise to base your figures on how many square feet of work an average worker can do in a day rather than base it on your most productive worker because once you know that, you can estimate labor costs no matter the season or year. A good rule of thumb is to assume an average worker can complete about 300 to 350 square feet of concrete work a day.

In general, you’ll need to add all of the following labor hours (and associated costs) to your concrete takeoff:

  1. Mixing: the cost to transport mixed concrete into the mixer and the cost of a mixer itself
  2. Transportation: the cost to transport mixed concrete to the location
  3. Compaction: the cost involved in using compaction machines/vibrators
  4. Reinforcement: the cost of steel and labor for cutting and tying of rebars
  5. Formwork: the cost of formwork for beams, columns, or slabs
  6. Skilled Labor: the manpower required to mix, transport, compact, and finish concrete but also be factored into the labor cost

Step 3: Determining Overhead

The next step is to add in overhead costs. Overhead costs are any costs incurred that are not related to labor, direct materials, or production, such as running your back office, vehicles, upkeep, advertising, and other expenses. And don’t forget your time meeting with the client and preparing the estimate! That’s all part of what has to be billed.

Calculating overhead can be intimidating at first, but it’s not too difficult. First, you have to know what your overhead expenses are for a year. Include all salaries for anyone who works on the business's back end, like the bookkeeper or secretary.

For larger overhead expenses such as a work vehicle or truck lease, you can also prorate the expense and include it as a cost on your concrete takeoff. For example, if you have a truck that you use regularly for your business and expect it to last 10 years, your yearly cost is 10% of the total cost (1 out of 10).

If you know your total annual overhead expenses, you can also determine what percent of the year you’ll work on a specific concrete project and then factor that percentage into your concrete estimate costs. If your concrete job will last 4 weeks on a large project and you typically work 50 weeks a year, you’ll know that the current takeoff should include 8% of your total overhead expense.

Step 4: Calculating Profitability

And of course, you need to make a profit. How much do you expect to make for the year, above and beyond your expenses? If you want to stay in business, you absolutely need to include markup in your final takeoff.

To factor in profit, start by determining the overall margin for your business, usually somewhere between 2 and 10% in the construction industry, and then include a percentage of this total annual number just like you did for overhead costs.

Of course, when you write up your final takeoff, estimate, or quote, you won’t include sections for “overhead” and “profit”. Instead, you’ll fold these costs into labor costs on your final concrete takeoff.

Considerations When Performing Concrete Takeoff

When you're undertaking a concrete takeoff, there are many important considerations that you should take into account that can impact your estimate:

  • Is the project a good fit for your company's experience? If you've done a lot of shotcrete as your mainstay, going to a large paving or pump and fill project may be problematic. It may not be a good fit for your knowledge base, experience, and skill set. Though it's okay to use these approaches to break into new market sectors with the potential for profit loss and a solid learning curve, it's better to start small and pass on projects that won't be a good fit. Keep with what you know to get the work done efficiently and profitably.
  • Look at the plans for anything odd, unique or unusual. If you need to add special labor, materials, or other resources, try to determine if you can complete that part of your project while making a profit. Consider subcontracting that part if it's going to tie your crew down. Adding a change order later for something you missed on the plans during the takeoff stage can look unprofessional.
  • Start at the bottom with anchors, rebar, reinforcing mesh, and similar materials. Some companies will use different colored markers, pencils, and pens to mark up paper plans, then transfer the counts they've made to a separate list. If you try this, make sure you're consistently marking up the plans the same way, then double-check the work to make sure it's correct.
  • Look at what type and how much concrete will be needed. Does that slab need to be 3,000 or 5,000 PSI? What about those high-strength columns? Look at all of the different areas you'll need to be worked on, then calculate each area and type of concrete to be able to calculate the cubic yardage, then reach out to your suppliers to determine the cost of the materials.
  • Do you need any unusual materials? If the project calls for colored concrete, reinforcing fibers, or other materials that are not usual, make sure that you take a careful look at the specifications. Do the materials need special handling? Will you need to bring in additional labor to get the job done right? Take a close look at issues such as these to make sure they don't eat into your profits.
  • What about odd parts of the project that will require more or specialized labor? If you need to take special care to finish up a particular project, need to hire a subcontractor to handle a specialty concrete product, or have to pay overtime or a shift differential for a highway job that can only be poured at night, make sure that you note it in your takeoff. You could also consider specialty offsets for LEED construction under these areas.
  • Once you've completed your takeoff, walk away, then review your calculations or have someone else check them for accuracy. Do you have accurate supplier costs? Are the labor and material takeoffs reasonable? Take the time to walk through the plans mentally to see if you've missed anything. This could be as simple as water tanks for a remote peagravel pour, excavation equipment rentals, or similar aspects.

Concrete Takeoff Services Save Time and Eliminate Errors

While we’ve just provided a detailed guide on how to complete an accurate concrete takeoff or estimate, the process is complicated, time-consuming, and stressful. Beyond determining your materials and labor, you’ll have to answer so many questions during the process. What should your overhead be? How much profit should you add? What do you need to include with the paperwork to submit the final proposal? You probably didn't get into business for all of this hassle.

When it comes to your concrete business, what you do best is run your company and get concrete placed and finished. What if you could continue to focus on those aspects of your business while still keeping a regular stream of projects coming through the door without having to split your attention to the next five projects you need to bid?

If you work with 1build, you'll be able to do just that. Our team of professional estimators can take care of making sure you've got a solid, accurate concrete takeoff that takes into account the many factors of each project that makes it unique and difficult to bid. We can provide these results one project at a time to help you with your overflow or under a monthly access fee to handle all of your estimating needs.

We'll take into account your overhead, desired profitability, and expected expenses to help ensure that you're not only bidding competitively but profitably as well. We'll help reduce that overhead by allowing you to focus on spending time on the jobsite instead of stuck in the office.

If you're ready to make the move to winning more projects at a profitable price margin, 1build is here to help. Please feel free to reach out today with any questions, to schedule a demo or to set up your account to start improving your bid numbers.

Concrete Takeoff: The Ultimate Guide to Estimating your Next Concrete Job | 1Build (2024)

FAQs

How to do a quantity take off? ›

Manual Quantity Takeoff

With this method, estimators reference the construction plans to measure and list all the required physical materials and labor. Then, they look at the plans and use various formulas and calculations to determine the exact quantity of each item.

How do you calculate concrete take off? ›

You'll measure off the area and calculate the volume of concrete needed: length x width x depth. You'll also want to add in an additional cost for waste and spillage, which is roughly 10% of the total volume. To determine the amount of bags of concrete you'll need, simply multiply the bags by the total cost.

How do I work out how much concrete I need? ›

You will want to:
  1. Determine how thick you want the concrete.
  2. Measure the length and width that you'd like to cover.
  3. Multiply the length by the width to determine square footage.
  4. Convert the thickness from inches to feet.
  5. Multiply the thickness in feet by the square footage to determine cubic feet.

What is concrete takeoff? ›

What is a Concrete Takeoff? A takeoff is simply a complete list of all materials needed, and the quantities of each, based on the plans and specifications.

How do I estimate concrete work? ›

Calculating the volume for concrete requires using three dimensions: length times width (which is area) times the height (thickness) or L x W x H. If you are using feet as your standard unit of measurement, this formula will give you the volume of concrete in cubic feet.

How to do a take off manually? ›

Manual. This is a traditional method of doing takeoffs involving paper plans, a scale ruler, measuring tape, a calculator, and a paper or spreadsheet. The estimator must review the project plans meticulously, and manually count and list all materials needed for each trade.

What is a take-off in estimating? ›

A construction takeoff is a process of listing and measuring the materials required for the project to calculate the cost to complete it. The construction takeoff is the first step in the estimation process and involves quantifying the materials necessary to start and execute the job.

How do you calculate concrete removal? ›

Concrete demolition and removal typically ranges from $2 to $6 per square foot, so a 500-square-foot floor might cost from $1,000 to $3,000.

How do you calculate cement jobs? ›

The formula for estimating the volume of concrete in cubic yards needed on a project is straight forward, though it will definitely require a calculator. Simply multiply the length by the width by the depth of the desired slab in inches, then divide by 1728.

How much does a 30x40 concrete slab cost? ›

The average cost is $4 to $8 per square foot. The median price is about $6 per square foot. Based on these averages, you may pay $4,800 to $9,600 with a median estimate of $7,200.

How to calculate the concrete quantity? ›

How do I calculate how much concrete I need? To find the amount of concrete you need, use our concrete calculator or this simple volume formula: Length × Width × Thickness. Measure your project and multiply the dimensions to get cubic feet or meters. Divide by 27 to convert cubic feet to cubic yards.

What is the formula for free concrete calculator? ›

Cubic feet formula: Length * width * depth/thickness

For example, if your slab is 10' wide and 10' long with 1' of depth, the volume of your slab would be 100 cubic feet (10x10x1 =100).

How much will 10 yards of concrete cover 4 inches thick? ›

A general rule of thumb is on cubic yard of concrete will cover the following areas: 4″ thick – covers 81 square feet. 5″ thick – covers 65 square feet. 6″ thick – covers 54 square feet.

How to calculate concrete labor? ›

How to calculate labor cost in construction
  1. Break down the project into individual tasks. ...
  2. Estimate the time required for each task. ...
  3. Determine the hourly wage rate for each worker. ...
  4. Multiply the time for each task by the hourly wage rate. ...
  5. Add up the total labor cost for all tasks.
Jun 14, 2023

What is the best machine to remove concrete? ›

A jackhammer is an ideal power tool used for concrete demolitions, and four subcategories of jackhammers exist, including rotary, demolition, combination and breaker options. Each specializes in a particular task for various applications.

What is it called when you remove concrete? ›

Concrete is a beautiful addition to any home, but when it starts to crumble or break, it can become an eyesore. While you might want to kick your concrete to the curb, concrete demolition is a physically demanding DIY job. To make the process easier on you, you'll need some tried-and-true strategies under your belt.

How to calculate concrete takeoff? ›

Measure one area at a time, for example, slabs, wall foundations, foundation walls, and column foundations. Next, calculate the volume of concrete required for an area by multiplying the length by the width and depth. Then, add about 10% of the total volume to cover the additional cost of waste and spillage.

How to estimate job cost? ›

Using the formula Total job cost = Direct materials + direct labor + applied overhead, Jared adds $400 + $660 + $366.74 to arrive at a total job cost of $1,426.74. This is the amount that Marissa pays Jared for her dining room table.

How to estimate concrete price? ›

Concrete is a relatively cost-effective material when compared to stone or brick. Anticipate spending about $6 per square foot for the raw material, ranging from around $4 to $8 per square foot, depending on variables like labor and the thickness of the concrete.

What is an example of a quantity take off? ›

Example:For a commercial building project, assembly quantity takeoff might involve quantifying assemblies like: Exterior wall systems (including framing, insulation, cladding) Floor systems (including concrete, structural steel, decking) HVAC systems (including ductwork, units, controls)

What is the formula to calculate quantity? ›

You calculate the net quantity according to one of the following formulas: If the physical quantity is Length: Net quantity = length x number of units. If the physical quantity is Area (m2): Net quantity = length x width x number of units. If desired, you can overwrite the calculated net quantity with a different value.

What is a quantity take off standard? ›

Quantity takeoffs (QTO) refers to the estimation of materials, resources, and labor needed to complete a construction project. You review the project plans and take off information about what physical materials the architect, engineer or draftsperson specifies to assemble the project.

How to do a take-off list? ›

  1. Step One – Review Your Project Plans. ...
  2. Step Two – List The Required Materials. ...
  3. Step Three – Measure The Project Components. ...
  4. Step Four – Calculate Quantities Of Materials. ...
  5. Step Five – Determine Your Costs. ...
  6. Step Six – Create A Takeoff Sheet.

Top Articles
Cupid Drawing - How To Draw Cupid Step By Step
70+ Small Tattoos with Big Meanings You’ll Fall in Love with - Tattoo HQ
Omega Pizza-Roast Beef -Seafood Middleton Menu
What Is Single Sign-on (SSO)? Meaning and How It Works? | Fortinet
Hotels
St Als Elm Clinic
Soap2Day Autoplay
The Wicked Lady | Rotten Tomatoes
FIX: Spacebar, Enter, or Backspace Not Working
Find your energy supplier
Yesteryear Autos Slang
83600 Block Of 11Th Street East Palmdale Ca
Marion County Wv Tax Maps
Bjork & Zhulkie Funeral Home Obituaries
6813472639
Craftology East Peoria Il
Nissan Rogue Tire Size
Mflwer
111 Cubic Inch To Cc
Georgia Vehicle Registration Fees Calculator
Craigslist Free Stuff Merced Ca
Pearson Correlation Coefficient
Project Reeducation Gamcore
Globle Answer March 1 2023
Danielle Ranslow Obituary
Why Are Fuel Leaks A Problem Aceable
Telegram Voyeur
14 Top-Rated Attractions & Things to Do in Medford, OR
Access a Shared Resource | Computing for Arts + Sciences
TMO GRC Fortworth TX | T-Mobile Community
Trinket Of Advanced Weaponry
Frank Vascellaro
Funky Town Gore Cartel Video
Kamzz Llc
Craigslist Dallastx
3400 Grams In Pounds
Craigslist Pets Huntsville Alabama
Rage Of Harrogath Bugged
Bernie Platt, former Cherry Hill mayor and funeral home magnate, has died at 90
Sun Tracker Pontoon Wiring Diagram
Dinar Detectives Cracking the Code of the Iraqi Dinar Market
2132815089
Pa Legion Baseball
Sig Mlok Bayonet Mount
Citizens Bank Park - Clio
What is 'Breaking Bad' star Aaron Paul's Net Worth?
Phone Store On 91St Brown Deer
Devotion Showtimes Near Showplace Icon At Valley Fair
Mcoc Black Panther
Model Center Jasmin
Superecchll
Edict Of Force Poe
Latest Posts
Article information

Author: Sen. Emmett Berge

Last Updated:

Views: 6072

Rating: 5 / 5 (60 voted)

Reviews: 91% of readers found this page helpful

Author information

Name: Sen. Emmett Berge

Birthday: 1993-06-17

Address: 787 Elvis Divide, Port Brice, OH 24507-6802

Phone: +9779049645255

Job: Senior Healthcare Specialist

Hobby: Cycling, Model building, Kitesurfing, Origami, Lapidary, Dance, Basketball

Introduction: My name is Sen. Emmett Berge, I am a funny, vast, charming, courageous, enthusiastic, jolly, famous person who loves writing and wants to share my knowledge and understanding with you.